With the 45-foot deepening in place, the Corps has begun the next
phase of deepening channels in thePort - the Harbor Deepening Project
- deepeningkeychannels to 50 feet. The Corps has already initiated work
in the Kill Van Kull, deepening the western two thirds of this
waterway, and in the Ambrose Channel, the main entrance channel
into the Port. Deepening work in Newark Bay and the Anchorage Channel is expected to begin by early 2007.
The current schedule for the Harbor Deepening
Project calls for completion of all channels to 50 feet by 2014.
The Corps of Engineers has substantially completed the deepening
of the PortJersey Channel to 41 feet and is planing to begin construction
of the 50-foot deepening in early 2007. The dredging, sponsored
by the State of New Jersey, will improve access to the privately
owned Global Marine Terminal in Jersey City and a planned second
facility adjacent to Global. Completion is estimated for 2008.